Railway Project

If anything can be called the lifeline of Navi Mumbai, it's the city's suburban railway network. It's a unique rail project involving CIDCO and Indian Railways, with CIDCO and Railways sharing the expenditure on a ratio of 67:33. Covering a length of 200 km and occupying 900 hectares of land, the network is planned with 6 separate corridors and 30 stations.

The 6 rail corridors in Navi Mumbai are:

1. Mankhurd-Belapur-Panvel (29 km corridor connecting
    Mumbai to Navi Mumbai) (commissioned)

2. Thane-Turbhe-Nerul / Vashi (23 km corridor connecting
    Thane to Navi Mumbai)

3. Kalwa-Turbhe (goods line commissioned)

4. Belapur / Nerul-Uran (work in progress)

5. Mansarovar-Taloja (planned)

6. Panvel-Uran (planned)

Direct access from residential to railway station by foot, convenient interchange facility from one corridor to another, double discharge platforms at every station, easy to follow routes, and comfortable and pleasant journeys form the key features of the commuter railway system in Navi Mumbai.

Mankhurd - Belapur - Panvel Railway Corridor

The Mankhurd - Belapur - Panvel rail corridor connects Navi Mumbai with Mumbai and was commissioned - upto Vashi in May 1992; upto Nerul in Feb 1993; up-to Belapur in June 1993; CST to Panvel (Single Line) Commuter Rail Service was commissioned on 29th June, 1998 and double line on 14th April, 2000. This corridor is 29 km in length and consists of 9 Stations, 9 ROB's and 1 RUB (Road Under Bridge) and 1 Tunnel (near CBD Belapur Station) and is one of the cornerstone in the development of Navi Mumbai.

Thane - Turbhe - Nerul/Vashi Railway Corridor

The Thane - Turbhe - Nerul/Vashi rail corridor connects Thane with Navi Mumbai and is 23 kms long; the corridor's construction commenced on October 1995 and was fully commissioned for commuter traffic on 9.11.2004. The corridor consists of 10 stations and has three major ROB's which are: Turbhe Link Road that connects Thane-Vashi-Nerul via Road; Khairane ROB near DAKC; and the Mahape ROB.

Belapur / Nerul- Seawood - Uran Railway Corridor

The Railway Project between Nerul and Belapur - Seawood - Uran was approved by Ministry of Railways and CIDCO Board and the work on the project began in July 1997. However, due to various unforeseen reasons, the work was delayed and hence stalled, until recently when the project was revived after the tripartite agreement between Railways, CIDCO and Govt. of Maharashtra was executed on 29.07.2011. The total length of the corridor is 27 km and consists of 10 stations; 4 major bridges; 5 ROBs; Provisions are made for one arm of the railway line to go to Belapur station from Sagarsangam (Kille).

Vashi Railway Bridge

The Vashi Railway Bridge is the connecting link between Mumbai and Navi Mumbai, connecting both the twin cities and is a major influence in the commercial development of Navi Mumbai and to an extent that of Mumbai. The bridge over the Thane Creek helped the inhabitants of Navi Mumbai to commute to Mumbai for work and was a major reason for people to come to Navi Mumbai for residential purposes. All in all, the Vashi Bridge essentially proved to be a vital catalyst in Navi Mumbai's development.

Railway Stations

When business is concentrated around a station which is a trademark scenario around major Railway Stations in India. Navi Mumbai had something totally innovative to offer. CIDCO, by converting the space above the railway station into a commercial complex, redefined architectural innovation and took it a step further. CIDCO has pioneered the concept of the 'railway station cum commercial complex' in Navi Mumbai. State-of-the-art offices and commercial facilities occupied air space above railway stations in this groundbreaking concept. It not only gave a new dimension to an otherwise routine architecture, but has also generated employment opportunities, resulting in massive growth centre's around the city, such as the ITC and IIP in CBD Belapur and Vashi respectively.

With the involvement of prominent architects in designing the projects, CIDCO used the latest construction technology available to ensure that these railway complexes in Navi Mumbai become modern architectural marvels. Railway Stations - The Commercial Enclave of Navi Mumbai!

Vashi Station

Vashi Railway Station is the gateway station to Navi Mumbai located in Sector-30A of Vashi Node and on south of Sion-Panvel Express Road.

It caters to the passenger demand of Vashi node, Sector 1 to 30 with present population of 1,09,524.

It is the most magnificent of all the station complexes.

The commercial complex has been converted into an International InfoTech Park in collaboration with Software Technology Park India (STPI).Vashi station also houses beautifully landscaped forecourt area and well-planned area for all modes of transport like public buses, autorickshaws, taxies, private cars etc.

This station caters for two corridors viz. Mankhurd-Belapur & Thane-Turbhe-Vashi.

Salient Features
Prime Consultant & Architect M/s. Pheroz Kudianwala Consult Engineers
Structural Designer M/s. Dubon Project Engineering Pvt. Ltd.
Total gross built up area 75,188 Sq.M.
Commercial complex area 70,380 Sq.M.
Railway area 4708 Sq.M.
Two Subways 7.0 M. wide.
Platforms 5 Nos. (for Double discharge facility)
Two end platforms 8.0 M. wide.
Three island platforms 12.0 M. wide.
Supervision M/s. IRCON, Navi Mumbai Unit through
CIDCO
Contractor M/s. AFCONS,
M/s N.B.C.C., M/s. Klassic Construction Co.
M/s. Gulraj Construction Co
M/s. U.P.R.N.N. Ltd.
Details Of Commercal Area
1. Total Area Turbhe
18 60,702 Sq.mtr.
2. Office premises Darave
3. Shopping Arcade 9678 Sq.mtr.


























Sanpada Station

Sanpada Railway Station Complex is located in Sector 3, Sanpada node, adjacent to Sion-Panvel Expressway It caters to the passenger demand of Sanpada node, Sector 1 to 8 and 13 to 18 and Agricultural Produce Market at Vashi Sector-19

Station complex consists of shopping area on the ground floor and well-integrated shops/ office premises on the first and second floors This station caters for two corridors viz. Mankhurd-Belapur & Thane-Turbhe-Vashi.
Salient Features
Prime Consultant & Architect M/s. Ratan J. Batliboi.
Structural Designer M/s. Shirish Patel & Associates.
Total gross built up area 24,770 Sq.M.
Commercial complex area 19,210 Sq.M.
Railway area 5560 Sq.M.
Two Subways 7.0 M. wide.
Through vehicular underpass 7.0 M. wide.
Platforms 5 Nos. (for Double discharge facility)
Two end platforms 8.0 M. wide.
Three island platforms 12.0 M. wide.
Supervision M/s. IRCON, Navi Mumbai Unit through
Navi Mumbai Unit through CIDCO
Commercial Complex – CIDCO
(Railway Projects Department)
Contractor M/s. Vatan Singh & Co.,
M/s. Navratandas & Co
M/s. Kalpana Structcon.
Details Of Commercal Area
1. Total Area 19,210 Sq.mtr.
2. Ground Floor 4,195 Sq.mtr.
3. Upper floors 11,055 Sq.mtr.
4. Cafeteria and Marriage halls 3,960 Sq.mtr.
Present Status
Railway station commissioned on 09.02.1993 by Shri Birendra Vishnu, AGM, Central Railway







































Juinagar Station

Juinagar Railway Station Complex is located in Sector 11, Sanpada node, adjoining the Sion-Panvel Expressway and caters the passenger demand of Sectors 9 to 12 and 20 to 25 of Sanpada node and industrial complex in the nearby area.

It is the most attractive station complex in terms of location as well as aesthetics, thereby frequently used for film shootings.

Station complex consists of shopping area on the ground floor and well-integrated shops/ office premises on the first and second floors.

This station caters for three corridors viz. Mankhurd-Belapur, Thane-Turbhe-Nerul & Thane-Nerul-Uran.

Salient Features
Architect M/s. Ratan J. Batliboi.
Prime Consultant & Structural Designer M/s. Shirish Patel & Associates.
Total gross built up area 9,838 Sq.M.
Railway area 2,958 Sq.M.
Two Subways 7.0 M. wide.
Platforms 7 Nos. (for Double discharge facility)
Two end platforms 8.0 M. wide.
Five island platforms 12.0 M. wide.
Supervision M/s. IRCON Navi Mumbai Unit through CIDCO
Navi Mumbai Unit through CIDCO
Contractor M/s. N.B.C.C.
Details Of Commercal Area
1. Total Area 6,880 Sq.mtr.
2. Ground Floor 3,160 Sq.mtr.
3. Upper floors 1,860 Sq.mtr.
4. Cafeteria and Marriage halls 1,860 Sq.mtr.
Present Status
Railway station commissioned on 09.02.1993 by Shri Birendra Vishnu,AGM, Central Railway


























 Belapur- Station


Belapur Railway Station Complex is the largest among the commercial complexes in Navi Mumbai. It is located in the CBD (Central Business District), Sector 11, which has tremendous potential for business growth.

It caters to the passenger demand of CBD-Belapur node, Sector 1 to 31, the present population is 41,516 Office premises are provided above deck level from 3rd to 7th floor.The office complex is attached with a sprawling shopping arcade located at ground & deck level.

Facility has been provided for helicopter landing on the deck. This station caters for two corridors viz. Mankhurd-Belapur-Panvel & Nerul/Belapur-Uran.

Salient Features
Architect M/s. Pheroz Kudianwala Consultants
Structural Designer M/s. Rajani Associates.
Total gross built up area 1,16,123 Sq.M.
Commercial complex area 93,498 Sq.M.
Railway area 22,625 Sq.M.
Two Commuter FOBs 7.0 M. wide.
One through FOB for pedestrians
Supervision M/s. IRCON Navi Mumbai Unit through CIDCO
Contractors M/s. K.N. Dadina, M/s. Shree Kumar & Co., M/s. N.B.C.C., M/s. Puri International, M/s. V.R. Mittal.
Details Of Commercal Area
1. Total Area 93,498 Sq.mtr.
2. Ground Floor 74,632 Sq.mtr.
3. Upper floors 13,450 Sq.mtr.
4. Restaurants 5,416 Sq.mtr.
5. Service towers 10 towers.
Present Status
Railway station commissioned on 16.06.1993 by Shri R. C. Sinha, M.D. CIDCO & Shri Y. P Anand Hon.Chairman, Railway Board



























Kharghar Station

Kharghar is a Residential and Commercial Node.Strategically located in the centre of the CBD of Navi Mumbai.The Railway Station caters to the passenger demand of Kharghar node, Sector 1 to 40 and ultimate population of 3.50 lacs.

The proposed International Airport is about 4 kilometers away.Project consists of Construction of Railway Office Building, Gigantic Entrance Portal Foyer, Parking Deck above the Platform ( for Two Wheelers & 4 Wheelers), utility structures & Landscaped Forecourt Area.

This station caters for two corridors viz. Belapur-Panvel & Ring Railway. For the first time, area above railway platforms has been used for parking vehicles.

Salient Features
No. of Platforms 5 nos. (3 Island + 2 End) for double discharge facility
Length of platform 270 mtrs for 12 cars EMU rakes.
No. of Commuter Subways 2 nos. (7 m. Wide each)
Station Building
Railway facilities & Offices 1475 sq.m
Entrance foyer area 2,300 sq.m.
Forecourt area 23,100 sq.m.
Parking Deck 19,300 Sq.m. (Cars - 450 nos. + 2 wheelers -750 nos.)
Prime Consultant M/s. Shirish Patel & Associates Consultants Pvt. Ltd. Mumbai.
Achitect M/s. Ratan J. Batliboi
Supervision M/s. CIDCO (Railway Project Department)
Contractors M/s. Vatan Singh & Co. for railway offices, M/s. L&T Pvt. Ltd. for platform and parking deck
Ramps connecting to the Parking Deck 2,400 sq.m.
(underpass below expressway and railway line for light vehicles)
Present Status
Temporary platform and booking offices etc. were commissioned for suburban railway services in January, 1995.Station Building & platform structure inaugurated by Hon’ble CM of Maharashtra on 12-06-2004.







































Mansarovar Station

Located about 2 kms. West of the Sion-Panvel Expressway.
In vicinity of proposed international airport.

This station will cater for three corridors as under
Operating Corridor CST - Panvel, third station from Belapur & Panvel.
Proposed Corridor (AsTerminus) Mansarovar - Taloja
Proposed Corridor Railway ring route
Salient Features
Architect M/s. Shashi Prabhu & Associate, Mumbai.
No. of Platforms 7 nos.(5 Island + 2 End) for double discharge facility
No. of Commuter Subways 2 nos. (7 m wide)
Railway Office Area 3,609 Sq.M.
Forecourt Area 1,03,410 Sq.M.
Present Status
Planned to commission the station with bare minimum facilities on CST-Panvel corridor shortly.



































Turbhe Station

Turbhe is the fifth railway station at 15.28km away from Thane railway station on Thane Turbhe Nerul / Vashi railway line.

This is a Junction station giving access to Vashi & Nerul from Thane. This station is located in sector-20 of Vashi node at an important junction of Vashi link road and thane – Belapur road.

The station serves the population of Vashi node, Turbhe, APMC market on the west side & Thane-Belapur industrial belt on the cast side.

Salient Features
Platforms 5nos, (2 End + island platforms)
Length of platform 210m. +60m (Future development
Subways
Commuter subway 2 nos. (7.0 m wide, 66 m. long)
Pedestrian subway 1 no(7.0 m wide, 66 m. long)
Station Building
Total Area TBR Side800sq. m Nodal side90sq. m
Platform & concourses Finishing with Andhra stone flooring & glass mosaic tiles cladding.
Forecourt Area TBR side – 5600 sq.m Nodal side – 3840 sq. m
Architects M/s. Hafeez Contractor
Structural proof consultant M/s. Certification Engineers India Ltd.
Spervision Railway project department of CIDCO ltd.(ISO 9001. 2000 certified)
Agencies
Platform roofing M/s. BE Billimoria & Co. Ltd
Other civil works M/s. Klassic Construction Co.
Finishes M/s. Suyog Granites & Marbles
Forecourt M/s. Aswini Infradevelopments P. Ltd.





























Koparkhairane Station

Koparkhairane is the Forth Railway Station at 12.11 km away from Thane Railway Station on Thane-Turbhe-Nerul/Vashi Railway Line. It is located in Sector 8A of Koparkhairane Node.

The site is accessible from Thane-Belapur Road from eastern side and 30 m. road from the nodal side.

This railway station will cater to the passenger traffic demand generated by Thane-Belapur Industrial Belt which is on the east side and commercial and residential population of Koparkhairane which is on the west side.

Salient Features
Platforms 5nos, (2 End + island platforms)
Length of platform 210m. +60m (Future development
Subways
Commuter subway 2 nos. (7.0 m wide, 66 m. long)
Pedestrian subway 1 no(7.0 m wide, 66 m. long)
Station Building
Total Area TBR Side800sq. m Nodal side90sq. m
Platform & concourses Finishing with Andhra stone flooring & glass mosaic tiles cladding.
Forecourt Area TBR side – 5600 sq.m Nodal side – 3840 sq. m
Architects M/s. Hafeez Contractor
Structural proof consultant M/s. Certification Engineers India Ltd.
Spervision Railway project department of CIDCO ltd.(ISO 9001. 2000 certified)
Agencies
Platform roofing M/s. BE Billimoria & Co. Ltd
Other civil works M/s. Klassic Construction Co.
Finishes M/s. Suyog Granites & Marbles
Forecourt M/s. Aswini Infradevelopments P. Ltd.




























Khandeshwar Station

Located in Sector-17, New Panvel (West) and to the West of NH4-B, i.e. the road connection to Nhava-Sheva.Its location is surrounded by important Nodes i.e. CBD on west, Panvel on southeast, New Panvel on east, Kalamboli Steel Yard & Warehousing Complex on north.The location is on the centre of Radiating Arterial Roads.

Project is designed on Park Concept with formal stately gardens, acting as lungs of the City.This station caters for two corridors viz. Belapur-Panvel & Panvel-Uran.

Salient Features
No. of Platforms 5 nos. (3 Island + 2 End) for double discharge facility
Length of Platforms 210 mts. + 60 mts. (for future development)
No. of Commuter Subways 2 nos. (7 m. Wide)
No. of Pedestrian & Vehicular subway 1 no. each (7 m wide)
Platform with Roof Area under Platform Arch Type Structural System 9212 Sq.m.
Station Building
Railway facilities & Offices 800 Sq.m.
Entrance Concourse 772 Sq.m. with polycorbonate sheet roofing
Forecourt Area 78,822 Sq.m.
Prime Consultant & Architect M/s. Stup Consultants Pvt. Ltd., Mumbai.
Supervision M/s. CIDCO (Railway Projects Department) (ISO 9001-2000 certified)
Contractors M/s. Manoj Constructions for railway offices
Details of Commercial Area
1. Total Area 14,130 Sq.mtr.
2. Ground Floor 5,090 Sq.mtr.
3. Upper floors 9,040 Sq.mtr.
Present Status
Temporary platform and booking offices etc. were commissioned for suburban railway services in January 1995.Railway Office Building work is completed.




































Panvel Station

Panvel is the centre of all industrial traffic in Navi Mumbai including JNPT It is an important junction for long distance trains and terminus for suburban trains from Mumbai CST.

Trains from 4 directions viz. Mumbai via Diva, Mumbai via Vashi (Suburban only), Uran and JNPT (Goods only), South i.e. Konkan Railway meet at Panvel.In addition Panvel is being connected to Karjat (28.85 km).

Suburban station building has been designed to provide operational facilities for Railways.The commissioning of suburban trains from Mumbai to Panvel has given great impetus to the development of Panvel and surrounding area.It is located adjoining the existing Panvel railway station of main line on its North.

The railway station caters to the passenger demand of New Panvel node sector-1 to 19 (East) New Panvel Trans Railway area and Panvel Municipal area.This station caters two corridors viz. Belapur-Panvel & Panvel-Uran.

Salient Features
No. of Platforms 5 nos. (3 Island + 2 End) for double discharge facility
Length of Platforms 270 mts. for 12 cars EMU rakes
Platform Roof Frustum of inverted pyramid made out of M.S. tubular section covered with zincalum and Polycarbonate sheets.
No. of Commuter Subways 1 no. (7 m. Wide)
No. of Foot Over Bridge 1 no. (4.9 m Wide)
Station Building
Terminal Building 2,710.05 sq.m.
Forecourt Area 77,495 Sq.m.
Prime Consultant & Architect M/s. Shashi Prabhu & Associates Consultants Pvt. Ltd. Mumbai.
Structural Consultant M/s. Vijay Bhise & Associates, Mumbai.
Proof Consultant M/s. U.D. Chande, Mumbai.
Agency M/s. B.G. Shirke Construction Technology Ltd., Pune
Supervision M/s. CIDCO (Railway Projects Department) (ISO 9001-2000 Certified)
Work awarded February, 2005
Present Status
Suburban Railway upto Panvel commissioned in June 1998.CST Panvel Double-Line Commissioned on 14-04-2000.Development of Suburban Railway Terminus Station started 02-02-2005.




































Ghansoli Station

Ghansoli is the Third Railway Station at 10.59 km away from Thane Railway Station on Thane-Turbhe-Nerul/Vashi Railway Line.

The Railway Station is located in Sector-2 of Ghansoli Node. The site is accessible from Thane-Belapur Road towards eastern side and 30 m road on the nodal side.

The predominant users of this station will be Thane Belapur industrial population on eastern side particularly the electronic zone and millennium park in MIDC.

Salient Features
Platforms 5 nos. (3 Island + 2 End) for double discharge facility
Length of Platforms 270 mts. for 12 cars EMU rakes
Platform Roof Frustum of inverted pyramid made out of M.S. tubular section covered with zincalum and Polycarbonate sheets.
No. of Commuter Subways 1 no. (7 m. Wide)
No. of Foot Over Bridge 1 no. (4.9 m Wide)
Station Building
Terminal Building 2,710.05 sq.m.
Forecourt Area 77,495 Sq.m.
Prime Consultant & Architect M/s. Shashi Prabhu & Associates Consultants Pvt. Ltd. Mumbai.
Structural Consultant M/s. Vijay Bhise & Associates, Mumbai.
Proof Consultant M/s. U.D. Chande, Mumbai.
Agency M/s. B.G. Shirke Construction Technology Ltd., Pune
Supervision M/s. CIDCO (Railway Projects Department) (ISO 9001-2000 Certified)
Work awarded February, 2005
Present Status
Suburban Railway upto Panvel commissioned in June 1998.CST Panvel Double-Line Commissioned on 14-04-2000.Development of Suburban Railway Terminus Station started 02-02-2005.




































Rabale Station

Rabale is the second Railway station at 8.285km away from Thane Railway station on Thane - Turbhe - Nerul/ Vashi Line.

Salient Features
Platforms 5 nos. (3 Island + 2 End) for double discharge facility
Total No. of Platforms 5 nos (IEnd + 1 & 1/2 Island platform constructed)
Length of Platform 210 m + 60 m (Future development)
PHASE I
Subways
No. of Commuter Subways 2 nos. (7 m wide, 66 m long each)
No. of Pedestrian cum vehicle 1 no. (5 m wide, 85 m long)
Station Building 670 sqm TBR
Forecourt Area 15,660 Sq.m. Thane, Belapur road Side 24,400 Sq.m. Nodal Side
Architects 2,710.05 sq.m.
Agencies M/s. Ess Vee Earthmovers (S&T rooms & forecourts)M/s. Unity Construction
Supervision Railway Project Department of CIDCO Ltd.(ISO 9001:2000 Certified)
Station Building
Finishes Alukobord cladding for external faces Galvalum with polycorbonate sheeting for platform roof.





































Airoli Station

Airoli is the First Railway Station 5.79 Km away from Thane Railway Station on Thane-Turbhe-Nerul/Vashi Line.

The Railway Station is located in sector-3 of Airoli Node abutting the Thane-Belapur road.

It will cater to passenger traffic demand generated by Thane-Belapur industrial zone which is on east side and residential & commercial zone of Airoli on the west. Airoli Station is transition station between Mumbai and Navi Mumbai.

Salient Features
Platforms
C/L 5 nos (IEnd + 1 & 1/2 Island platform constructed)
Length of Platform 210 m + 60 m (Future development)
PHASE I
Subways
No. of Commuter Subways 2 nos. (7 m wide, 66 m long each)
No. of Pedestrian cum vehicle 1 no. (5 m wide, 85 m long)
Station Building 670 sqm TBR
Forecourt Area 15,660 Sq.m. Thane, Belapur road Side 24,400 Sq.m. Nodal Side
Architects 2,710.05 sq.m.
Agencies M/s. Ess Vee Earthmovers (S&T rooms & forecourts)M/s. Unity Construction
Supervision Railway Project Department of CIDCO Ltd.(ISO 9001:2000 Certified)
Station Building
Finishes Alukobord cladding for external faces Galvalum with polycorbonate sheeting for platform roof.



































Mankhurd-Belapur Railway Line

Mankhurd - Belapur Railway project is the first joint venture Project of the State Govt. with the Ministry of Railways.

This project was taken up under the tripartite agreement executed between State Govt., CIDCO & Central Railways.

First time in India, right to exploit air space above the stations has been given to CIDCO to raise revenue for railway projects.

Station cum Commercial Complexes have been planned & constructed as State-of-art stations integrated with all facilities.

Cost of Railway Line with Railway area in the stations is shared by CIDCO and Railways in the proportion of 67% and 33% respectively.

Cost of commercial complexes in Navi Mumbai is entirely borne by CIDCO.

Salient Features
Length 18 km.
Project Cost of Commuter double line(67% : 33%) Rs. 440.87 crores(Base year 1990-91)
No. of tracks 2 nos.
No. of ROB’s a) 2 nos. - Part of Railway Project b) 3 nos. - Part of Nodal Development (100% cost borne by CIDCO)
No. of RUB’s 1 no.
No. of tunnels 1 no. (150 mtr. in length)
No. of Pedestrian cum vehicle 10 nos.
Major bridges 48 nos.
Thana Creek Bridge PSC Bridge of 35 spans (53.50 mtr. each)
Total length 1.80 km.
Reversal facility at Wadala Road Station For running Belapur-Andheri train.
Car shed facility at Sanpada
Stations
Railways stations 7 Nos.
Mankhurd 21.42 km. from CST
Vashi 28.91 km. from CST
Sanpada 30.08 km. from CST
Juinagar 31.95 km. from CST
Car shed facility at Sanpada 34.42 km. from CST
Seawoods Darave 35.80 km. from CST
Belapur 34.42 km. from CST
Present Status
Opening of Mankhurd-Vashi line by Shri. Venkatraman, Hon. President of India on 9th May, 1992. Opening of Vashi-Nerul line on 9th Feb. 1993.Opening of Nerul-Belapur line on 16th June, 1993. Opening of Computerised Reservation Centre at Belapur & starting of Belapur-Andheri local on 25th March, 1994.












































Belapur-Panvel Railway Line

Belapur - Panvel Railway Commuter Line is extension of Mankhurd-Belapur Railway Commuter line.

This Railway line provides Mass Rapid Transport facility to Kharghar Node, Steel Market at Kalamboli & Residential Complexes at Khandeshwar & Panvel.

Interchange facility is proposed at Mansarovar Station.

Belapur – Panvel line divides Navi Mumbai centrally and hence has a lot of potential for passenger traffic and is instrumental in increasing the land cost of a large area covered by this project.

Salient Features
Length 11 km.
Cost 1. Rs. 106.76 crores (fully borneby CIDCO) for Single line. 2. Rs. 279.83 crores (Base year 1994-95) for double line
Major Bridge Taloja Creek Bridge
No. of ROB’s 3 nos.
NH-4 ROB Completed in May 1997 (cost fully borne by CIDCO)
Matheran ROB Completed in November 1997 (cost fully borne by CIDCO)
NH-4B ROB Completed in June 2000 (under megacity project)
Stations
Railway stations 4 Nos.
hana Creek Bridge • Kharghar : 40.36 km. from CST • Mansarovar : 43.47 km. from CST • Khandeshwar : 45.37 km. from CST • Panvel : 48.83 km. from CST
Present Status
The single line is commissioned on 25-1-1995 up to Khandeshwar and inaugurated by Shri Ashok Bhatnagar, Chairman Rly. Board & Shri B. B. Sharma, MD (CIDCO) Single line extended upto Panvel & commissioned on 29th June, 1998 inaugurated by Shri Ram Naik, Hon C. Rly. Minister for state andShri Manohar Joshi, Hon. Chief Minister CST to Panvel (double line) Commuter Rail Service was commissioned on 14th April 2000































Nerul/Belapur-Uran Railway corridor

Belapur - Panvel Railway Commuter Line is extension of Mankhurd-Belapur Railway Commuter line.

This Railway line provides Mass Rapid Transport facility to Kharghar Node, Steel Market at Kalamboli & Residential Complexes at Khandeshwar & Panvel.

Interchange facility is proposed at Mansarovar Station.

Belapur – Panvel line divides Navi Mumbai centrally and hence has a lot of potential for passenger traffic and is instrumental in increasing the land cost of a large area covered by this project.

Salient Features
Length 27 km. approx..
Approved Cost By Railway Board Rs.1412.17 crores ( 2009 price level)
Date of start June / July - 1997
Number of stations 10
Names: Seawoods,Sagarsangam, Targhar, Bamandongari Kharkopar,Gavan,Ranjanpada, Nhavasheva,Dronagiri & Uran)
Road over bridges 15 Nos.
Track under bridge 1 No
Major bridges Important bridge of 751 m span across Panvel creek completed, 4 major bridges, one viaduct.
Number of rakes 11 Nos./td>
Platforms: 270 m platforms for four B.G. tracks to cater 12 car EMU rakes with double discharge facility.
Tripartite agreement between CIDCO, Govt. of Maharashtra and Railways and commercial development agreement between CIDCO and Railways signed on 29.07.2011

























Thane-Turbhe-Nerul/Vashi Rail Corridor

Thane-Turbhe-Nerul/Vashi railway line divides Navi Mumbai North-South Axis centrally and provides commuter service to various industries situated in Thane Industrial Belt on East side of Thane-Belapur Road and various residential nodes viz. Airoli, Rabale, Ghansoli, Koperkhairane, Turbhe on West side of Thane-Belapur Road and also to the rest of Navi Mumbai. This line starts from Thane across Kalwa Creek, and joins at Vashi the first station in Navi Mumbai across Thane Creek on Harbour line.

Salient Features
Project Cost 27 km. approx..
Single Goods Line 100% by CIDCO with MMRDA Finance Rs. 143.86 Crores
Commuter Double line Rs. 403.39 Crores
CIDCO 67%, C. Rly. 33% Share (271.92 Cr : 131.47 Cr.)
No. of Tracks 2 with 1676 mm (Broad gauge)
Road over bridges 5
Distances from Thane Airoli 5.79 Kms Rabale 8.29 Kms Ghansoli 10.59 Kms Koperkhairane 12.11 Kms Turbhe 15.27 Kms Sanpada 17.35 Kms Vashi 18.60 Kms Juinagar 17.65 Kms Nerul 20.12 Kms
Length of Platforms at Stations 210 m to accommodate 9 Car EMU rakes(Provision for 270 m for 12 Car EMU rakes)
Width of Platform at Stations Double Discharge Facility 12 m for Island Platform & 8m for End Platform
Permanent Way
Track Structure Consists of 60 Kg / 90 UTS new rails on Monoblock Concrete sleepers with a density of 1660 nos. per km on 300 mm ballast cushion.
Stabilising Stabilising lines to accommodate three rakes of 12 cars at Vashi and four rakes of 12 cars at Panvel have been planned.
1. Total Area 70,380 Sq.mtr.
2. Office premises 60,702 Sq.mtr.
3. Shopping Arcade 9678 Sq.mtr.
4. Service towers 12 Towers.